| Action Date | Action Description |
|---|---|
| Apr 15, 2005 | Assent Application Received |
| Apr 15, 2005 | Administrative Review for Completeness |
| May 10, 2005 | Team Review for Completeness |
| May 10, 2005 | Application Accepted |
| May 17, 2005 | 30 day Public Notice Issued |
| Jun 13, 2005 | US Army Corp of Engineers Permit Date |
| Jun 15, 2005 | US Army Corps of Engineers Approval Received |
| Jun 17, 2005 | Public Notice End Date |
| Jul 11, 2005 | Engineering Report |
| Jul 11, 2005 | Typist for Processing |
| Jul 11, 2005 | Executive Sign Off |
| Jul 11, 2005 | Sent to Photo Copy |
| Jul 11, 2005 | Permit Approved |
| Aug 18, 2005 | Land Evidence Date |
| Feb 26, 2007 | Modification Request |
| Feb 26, 2007 | Administrative Review for Completeness |
| Feb 26, 2007 | Team Review for Completeness |
| Mar 05, 2007 | HPHC Historical Preservation No Effect |
| Mar 06, 2007 | 30 day Public Notice Issued |
| Apr 06, 2007 | Public Notice End Date |
| Apr 26, 2007 | Typist for Processing |
| Apr 26, 2007 | Executive Sign Off |
| Apr 26, 2007 | Sent to Photo Copy |
| Apr 26, 2007 | Engineering Report |
| Apr 27, 2007 | Modification Approved |
| May 02, 2007 | Land Evidence Date |
| May 03, 2007 | US Army Corp of Engineers Permit Date |
| May 07, 2007 | US Army Corps of Engineers Approval Received |