| Action Date | Action Description |
|---|---|
| Jan 24, 2008 | Assent Application Received |
| Jan 28, 2008 | Administrative Review for Completeness |
| Feb 25, 2008 | Team Review for Completeness |
| Feb 25, 2008 | Deficient Application - Owner Notification Sent |
| Apr 07, 2008 | Deficiency Response Received |
| May 09, 2008 | Administrative Review for Completeness |
| May 12, 2008 | Team Review for Completeness |
| May 12, 2008 | Application Accepted |
| May 12, 2008 | Category A* (Docks) |
| May 21, 2008 | 30 day Public Notice Issued |
| May 22, 2008 | HPHC Historical Preservation No Effect |
| Jun 21, 2008 | Public Notice End Date |
| Jul 16, 2008 | Dock Meeting -- Approval |
| Jul 18, 2008 | Engineering Report |
| Jul 23, 2008 | Typist for Processing |
| Jul 23, 2008 | Executive Sign Off |
| Jul 23, 2008 | Sent to Photo Copy |
| Jul 23, 2008 | Permit Approved |
| Jul 23, 2008 | Biologist Report |
| Aug 04, 2008 | Land Evidence Date |
| Aug 05, 2008 | US Army Corp of Engineers Permit Date |
| Aug 07, 2008 | US Army Corps of Engineers Approval Received |