| Action Date | Action Description |
|---|---|
| Aug 05, 2008 | Assent Application Received |
| Aug 06, 2008 | Administrative Review for Completeness |
| Aug 06, 2008 | Team Review for Completeness |
| Aug 06, 2008 | Team Review for Completeness |
| Aug 06, 2008 | Application Accepted |
| Aug 07, 2008 | Biologist Report |
| Aug 07, 2008 | Engineering Report |
| Aug 08, 2008 | Typist for Processing |
| Aug 08, 2008 | Executive Sign Off |
| Aug 08, 2008 | Sent to Photo Copy |
| Aug 08, 2008 | Permit Approved |
| Sep 18, 2008 | HPHC Historical Preservation No Effect |
| Dec 02, 2008 | Land Evidence Date |