| Action Date | Action Description |
|---|---|
| Dec 30, 2009 | Maintenance Certification Request |
| Dec 31, 2009 | Administrative Review for Completeness |
| Jan 05, 2010 | Team Review for Completeness |
| Jan 05, 2010 | Team Review for Completeness |
| Jan 05, 2010 | Application Accepted |
| Jan 20, 2010 | Biologist Report |
| Jan 20, 2010 | Engineering Report |
| Jan 22, 2010 | HPHC Historical Preservation No Effect |
| Feb 01, 2010 | Typist for Processing |
| Feb 01, 2010 | Permit Approved |
| Feb 02, 2010 | Executive Sign Off |
| Feb 04, 2010 | Sent to Photo Copy |
| Jun 01, 2010 | Land Evidence Date |
| Jun 23, 2010 | Commencement of Work Notice received |
| Aug 02, 2010 | Modification Request |
| Aug 03, 2010 | Administrative Review for Completeness |
| Aug 03, 2010 | Team Review for Completeness |
| Aug 03, 2010 | Team Review for Completeness |
| Aug 03, 2010 | Application Accepted |
| Aug 03, 2010 | Objections/Comments Received |
| Aug 12, 2010 | 30 Day Appeal Notification to Owner |
| Aug 12, 2010 | HPHC Historical Preservation No Effect |
| Aug 18, 2010 | Biologist Report |
| Aug 18, 2010 | Engineering Report |
| Aug 23, 2010 | Modification Approved |
| Aug 25, 2010 | Typist for Processing |
| Aug 25, 2010 | Executive Sign Off |
| Aug 25, 2010 | Sent to Photo Copy |
| Sep 10, 2010 | Land Evidence Date |