| Action Date | Action Description |
|---|---|
| Water Quality Certification | |
| Jan 04, 2013 | Assent Application Received |
| Jan 07, 2013 | Administrative Review for Completeness |
| Jan 07, 2013 | Team Review for Completeness |
| Jan 07, 2013 | Team Review for Completeness |
| Jan 07, 2013 | Application Accepted |
| Feb 08, 2013 | Correspondence Received |
| Mar 08, 2013 | HPHC Historical Preservation Comments/Concerns |
| Feb 19, 2014 | Correspondence Received |
| Mar 14, 2014 | Additional Information Requested from Applicant |
| May 07, 2014 | Engineering Report |
| May 07, 2014 | Biologist Report |
| May 09, 2014 | Biologist Report |
| May 13, 2014 | Typist for Processing |
| May 13, 2014 | Permit Approved |
| May 14, 2014 | Executive Sign Off |
| May 14, 2014 | Sent to Photo Copy |
| May 16, 2014 | Land Evidence Date |
| May 28, 2014 | Duplicate Original Assent requested/mailed |