| Action Date | Action Description |
|---|---|
| Apr 07, 2016 | Assent Application Received |
| Apr 12, 2016 | Administrative Review for Completeness |
| Apr 15, 2016 | Team Review for Completeness |
| Apr 15, 2016 | Application Accepted |
| May 02, 2016 | 30 day Public Notice Issued |
| May 03, 2016 | HPHC Historical Preservation No Effect |
| Jun 02, 2016 | Public Notice End Date |
| Jun 09, 2016 | Additional Information Requested from Applicant |
| Sep 19, 2016 | Comments Received |
| Sep 28, 2016 | Plans Received |
| Sep 29, 2016 | Biologist Report |
| Sep 30, 2016 | Mail Agenda Notice |
| Oct 11, 2016 | Semi-Monthly Meeting Date Scheduled |
| Oct 25, 2016 | US Army Corps of Engineers Approval Received |
| Dec 01, 2016 | Legal Response/Decision |
| Dec 01, 2016 | 30 Day Appeal Notification to Owner |
| Dec 08, 2016 | Stipulation Package from Biologist |
| Dec 08, 2016 | Typist for Processing |
| Dec 09, 2016 | Executive Sign Off |
| Dec 09, 2016 | Sent to Photo Copy |
| Dec 09, 2016 | Permit Approved |
| Feb 06, 2017 | Land Evidence Date |