| Action Date | Action Description |
|---|---|
| Nov 01, 2021 | Assent Application Received |
| Nov 03, 2021 | Administrative Review for Completeness |
| Nov 05, 2021 | Bio Team Review for Completeness |
| Nov 05, 2021 | Application Accepted |
| Nov 05, 2021 | Project Manager |
| Nov 23, 2021 | HPHC Review Pending |
| Nov 23, 2021 | HPHC Historical Preservation No Effect |
| Nov 29, 2021 | Additional Information Requested from Applicant |
| Nov 30, 2021 | Additional Information Received |
| Dec 06, 2021 | Correspondence Mailed/Faxed/E-mailed |
| Dec 22, 2021 | Plans Received |
| Jan 05, 2022 | Biologist Report |
| Jan 06, 2022 | Permit Approved |
| Jan 06, 2022 | Typist for Processing |
| Jan 06, 2022 | Executive Sign Off |
| Jan 06, 2022 | Sent to Photo Copy |
| Jan 07, 2022 | Permit Mailed |
| Jan 12, 2022 | Land Evidence Date |