| Action Date | Action Description |
|---|---|
| Enforcement Compliance Inspection Required | |
| Jan 04, 2022 | Assent Application Received |
| Jan 07, 2022 | Administrative Review for Completeness |
| Jan 07, 2022 | CHA Worksheet received |
| Jan 12, 2022 | Bio Team Review for Completeness |
| Jan 24, 2022 | Application Accepted |
| Jan 24, 2022 | Project Manager |
| Jan 31, 2022 | Category B assigned |
| Feb 21, 2022 | 30 day Public Notice Issued |
| Feb 25, 2022 | HPHC Review Pending |
| Feb 25, 2022 | HPHC Historical Preservation No Effect |
| Mar 18, 2022 | Objections/Comments Received |
| Mar 21, 2022 | Objections/Comments Received |
| Mar 21, 2022 | Public Notice End Date |
| Aug 03, 2022 | Public Hearing Notices Mailed |
| Aug 17, 2022 | Engineering Report |
| Aug 17, 2022 | Supervisor Engineer SignOff |
| Aug 17, 2022 | Supervisor Biologist SignOff |
| Aug 18, 2022 | Executive Signoff of Staff Reports |
| Aug 23, 2022 | Council Approval Granted |
| Aug 23, 2022 | Semi-Monthly Meeting Date Scheduled |
| Oct 18, 2022 | Plans Received |
| Nov 14, 2022 | Stipulation Package by Engineer |
| Nov 15, 2022 | Legal Response/Decision |
| Nov 15, 2022 | 30 Day Appeal Notification to Owner |
| Jan 26, 2023 | Typist for Processing |
| Jan 26, 2023 | Executive Sign Off |
| Jan 26, 2023 | Sent to Photo Copy |
| Jan 26, 2023 | Permit Approved |
| Jan 27, 2023 | Permit Mailed |
| Feb 13, 2023 | Land Evidence Date |
| Sep 02, 2025 | Extension of Permit Request |