| Action Date | Action Description |
|---|---|
| Feb 14, 2022 | Assent Application Received |
| Feb 17, 2022 | Administrative Review for Completeness |
| Feb 17, 2022 | CHA Worksheet received |
| Feb 24, 2022 | Additional Information Requested from Applicant |
| Mar 28, 2022 | Deficient Application - Owner Notification Sent |
| Mar 28, 2022 | Bio Team Review for Completeness |
| Apr 06, 2022 | Note to File |
| Apr 11, 2022 | Deficiency Response Received |
| Apr 11, 2022 | Application Accepted |
| Apr 11, 2022 | Project Manager |
| May 03, 2022 | HPHC Historical Preservation No Effect |
| May 04, 2022 | Biologist Report |
| May 10, 2022 | Typist for Processing |
| May 10, 2022 | Executive Sign Off |
| May 10, 2022 | Sent to Photo Copy |
| May 12, 2022 | Permit Approved |
| May 12, 2022 | Permit Mailed |
| Jul 12, 2022 | Land Evidence Date |
| Apr 28, 2023 | Modification Request |
| May 05, 2023 | Administrative Review for Completeness |
| May 09, 2023 | Bio Team Review for Completeness |
| May 09, 2023 | Project Manager |
| Jun 06, 2023 | HPHC Historical Preservation No Effect |
| Jun 07, 2023 | Biologist Report |
| Jun 13, 2023 | Typist for Processing |
| Jun 13, 2023 | Executive Sign Off |
| Jun 13, 2023 | Sent to Photo Copy |
| Jun 15, 2023 | Modification Approved |
| Jun 16, 2023 | Permit Mailed |
| Jun 30, 2023 | Land Evidence Date |
| Nov 01, 2023 | Commencement of Work Notice received |