| Action Date | Action Description |
|---|---|
| US Army Corps of Engineers Approval Required | |
| Dock Post-Construction Certification by Engineer received. | |
| May 11, 2022 | Assent Application Received |
| May 17, 2022 | Administrative Review for Completeness |
| May 19, 2022 | Additional Information Requested from Applicant |
| May 19, 2022 | Correspondence Received |
| May 23, 2022 | Additional Information Received |
| May 23, 2022 | Correspondence Mailed/Faxed/E-mailed |
| Jun 16, 2022 | Correspondence Mailed/Faxed/E-mailed |
| Aug 01, 2022 | Deficient Application - Owner Notification Sent |
| Aug 01, 2022 | Bio Team Review for Completeness |
| Aug 02, 2022 | Plans Received |
| Jul 23, 2024 | Deficiency Response Received |
| Aug 02, 2024 | Bio Team Review for Completeness |
| Aug 02, 2024 | Application Accepted |
| Aug 26, 2024 | HPHC Historical Preservation No Effect |
| Aug 27, 2024 | Additional Information Requested from Applicant |
| Sep 11, 2024 | Plans Received |
| Oct 02, 2024 | 30 day Public Notice Issued |
| Oct 31, 2024 | Comments Received |
| Nov 02, 2024 | Public Notice End Date |
| Dec 18, 2024 | Correspondence Received |
| Jan 16, 2025 | Additional Information Received |
| Jan 16, 2025 | Biologist Report |
| Jan 17, 2025 | Typist for Processing |
| Jan 17, 2025 | Executive Sign Off |
| Jan 17, 2025 | Sent to Photo Copy |
| Jan 17, 2025 | Permit Approved |
| Jan 23, 2025 | Permit Mailed |
| Feb 07, 2025 | Land Evidence Date |