| Action Date | Action Description |
|---|---|
| Sep 16, 2022 | Assent Application Received |
| Sep 21, 2022 | Administrative Review for Completeness |
| Sep 22, 2022 | Bio Team Review for Completeness |
| Sep 26, 2022 | Project Manager |
| Sep 26, 2022 | Application Accepted |
| Sep 26, 2022 | Project Manager |
| Oct 18, 2022 | HPHC Historical Preservation No Effect |
| Nov 01, 2022 | Additional Information Requested from Applicant |
| Jan 17, 2023 | Additional Information Received |
| Jan 27, 2023 | Plans Received |
| Mar 15, 2023 | Biologist Report |
| Mar 27, 2023 | Typist for Processing |
| Mar 27, 2023 | Executive Sign Off |
| Mar 27, 2023 | Sent to Photo Copy |
| Mar 27, 2023 | Permit Approved |
| Mar 30, 2023 | Permit Mailed |
| Oct 31, 2023 | Land Evidence Date |