| Action Date | Action Description |
|---|---|
| Dec 14, 2022 | Assent Application Received |
| Dec 16, 2022 | Administrative Review for Completeness |
| Dec 21, 2022 | Application Accepted |
| Dec 21, 2022 | Project Manager |
| Dec 23, 2022 | Bio Team Review for Completeness |
| Jan 20, 2023 | HPHC Historical Preservation No Effect |
| Feb 09, 2023 | Additional Information Requested from Applicant |
| Feb 20, 2023 | Additional Information Received |
| Feb 20, 2023 | CHA Worksheet received |
| Mar 03, 2023 | Biologist Report |
| Mar 21, 2023 | Typist for Processing |
| Mar 21, 2023 | Executive Sign Off |
| Mar 21, 2023 | Permit Approved |
| Mar 22, 2023 | Permit Mailed |
| Mar 22, 2023 | Commencement of Work Notice received |
| Mar 23, 2023 | Land Evidence Date |