| Action Date | Action Description |
|---|---|
| Oct 02, 2024 | Buffer Zone Management Application Received |
| Oct 07, 2024 | Administrative Review for Completeness |
| Oct 11, 2024 | Bio Team Review for Completeness |
| Oct 11, 2024 | Project Manager |
| Oct 11, 2024 | Application Accepted |
| Oct 23, 2024 | HPHC Historical Preservation No Effect |
| Nov 26, 2024 | Additional Information Requested from Applicant |
| Apr 07, 2025 | Additional Information Received |
| Apr 30, 2025 | Biologist Report |
| May 02, 2025 | Typist for Processing |
| May 02, 2025 | Executive Sign Off |
| May 02, 2025 | Sent to Photo Copy |
| May 02, 2025 | Permit Approved |
| May 06, 2025 | Permit Mailed |
| May 09, 2025 | Land Evidence Date |
| Jun 13, 2025 | Commencement of Work Notice received |