| Action Date | Action Description |
|---|---|
| Feb 09, 2005 | Assent Application Received |
| Feb 10, 2005 | Administrative Review for Completeness |
| Feb 21, 2005 | Team Review for Completeness |
| Feb 21, 2005 | Application Accepted |
| Nov 08, 2005 | Engineering Report |
| Nov 10, 2005 | Typist for Processing |
| Nov 10, 2005 | Executive Sign Off |
| Nov 10, 2005 | Sent to Photo Copy |
| Nov 10, 2005 | Permit Approved |
| Jan 26, 2006 | Land Evidence Recording on Hold |
| May 23, 2006 | Land Evidence Date |
| Sep 17, 2024 | Modification Request |
| Sep 19, 2024 | Administrative Review for Completeness |
| Sep 23, 2024 | Eng Team Review for Completeness |
| Sep 23, 2024 | Bio Team Review for Completeness |
| Sep 23, 2024 | Project Manager |
| Sep 23, 2024 | Application Accepted |
| Sep 23, 2024 | Project Manager |
| Oct 10, 2024 | HPHC Historical Preservation No Effect |
| Oct 25, 2024 | 30 day Public Notice Issued |
| Nov 12, 2024 | US Army Corps of Engineers Project Number received. |
| Nov 25, 2024 | Public Notice End Date |
| Feb 28, 2025 | Typist for Processing |
| Feb 28, 2025 | Executive Sign Off |
| Feb 28, 2025 | Sent to Photo Copy |
| Feb 28, 2025 | Modification Approved |
| Feb 28, 2025 | Modification mailed |
| Feb 28, 2025 | Engineering Report |
| Feb 28, 2025 | Biologist Report |
| Mar 06, 2025 | Permit Mailed |
| Mar 13, 2025 | Land Evidence Date |