| Action Date | Action Description |
|---|---|
| Jun 01, 2005 | Assent Application Received |
| Jun 02, 2005 | Administrative Review for Completeness |
| Jun 16, 2005 | Deficient Application - Owner Notification Sent |
| Jul 20, 2005 | Deficiency Response Received |
| Jul 21, 2005 | Team Review for Completeness |
| Jul 21, 2005 | Application Accepted |
| Aug 01, 2005 | HPHC Review Pending |
| Aug 12, 2005 | Historical Preservation Approval Granted |
| Oct 12, 2005 | Additional Information Received |
| Oct 27, 2005 | Objections/Comments Received |
| Nov 14, 2005 | Biologist Report |
| Nov 14, 2005 | Correspondence Received |
| Nov 14, 2005 | Correspondence Received |
| Dec 28, 2005 | Engineering Report |
| Jan 03, 2006 | Supervisor Biologist SignOff |
| Jan 03, 2006 | Supervisor Engineer SignOff |
| Jan 05, 2006 | Executive Sign Off |
| Jan 13, 2006 | Mail Agenda Notice |
| Jan 23, 2006 | Continuance Requested by Applicant |
| Jan 23, 2006 | Continuance request by applicant granted by Director |
| Jan 24, 2006 | Ready to Schedule Semi-Monthly Meeting |
| Jan 24, 2006 | Semi-Monthly Meeting Date Scheduled |
| Feb 23, 2006 | Ready to Schedule Semi-Monthly Meeting |
| Feb 23, 2006 | Mail Agenda Notice |
| Mar 14, 2006 | Semi-Monthly Meeting Date Scheduled |
| Mar 21, 2006 | Mail Agenda Notice |
| Mar 28, 2006 | Semi-Monthly Meeting Date Scheduled |
| Mar 28, 2006 | Semi-Monthly Meeting Held |
| Apr 19, 2006 | Mail Agenda Notice |
| Apr 25, 2006 | Semi-Monthly Meeting Date Scheduled |
| May 11, 2006 | Continued Application by the Council |
| Jul 14, 2006 | Ready to Schedule Semi-Monthly Meeting |
| Jul 14, 2006 | Mail Agenda Notice |
| Jul 20, 2006 | Entry of Appearance Received |
| Jul 21, 2006 | Correspondence Received |
| Jul 25, 2006 | Semi-Monthly Meeting Postponed |
| Jul 25, 2006 | Semi-Monthly Meeting Date Scheduled |
| Jul 31, 2006 | Ready to Schedule Semi-Monthly Meeting |
| Jul 31, 2006 | Mail Agenda Notice |
| Aug 03, 2006 | Additional Information Received |
| Aug 08, 2006 | Semi-Monthly Meeting Date Scheduled |
| Aug 11, 2006 | Continued Application by the Council |
| Aug 11, 2006 | Mail Agenda Notice |
| Aug 22, 2006 | Semi-Monthly Meeting Date Scheduled |
| Aug 28, 2006 | Mail Agenda Notice |
| Aug 28, 2006 | Continued Application by the Council |
| Sep 08, 2006 | Mail Agenda Notice |
| Sep 12, 2006 | Semi-Monthly Meeting Date Scheduled |
| Sep 12, 2006 | Semi-Monthly Meeting Postponed |
| Sep 13, 2006 | Ready to Schedule Semi-Monthly Meeting |
| Sep 19, 2006 | Semi-Monthly Meeting Date Scheduled |
| Sep 19, 2006 | Semi-Monthly Meeting Held |
| Sep 19, 2006 | Council Approval Granted |
| Sep 25, 2006 | Stipulation Package by Engineer |
| Oct 17, 2006 | Stipulation Package from Biologist |
| Oct 17, 2006 | Typist for Processing |
| Oct 17, 2006 | Executive Sign Off |
| Oct 17, 2006 | Sent to Photo Copy |
| Oct 17, 2006 | Permit Approved |
| Oct 23, 2006 | Land Evidence Date |
| Nov 20, 2006 | Assent Correction Mailed |
| Nov 27, 2006 | 30 Day Appeal Notification to Owner |
| Nov 27, 2006 | Legal Response/Decision |
| Nov 29, 2006 | Land Evidence Recording on Hold |
| Jan 05, 2007 | Correspondence Received |
| Jan 31, 2008 | Correspondence Received |
| Jul 14, 2008 | Correspondence Mailed/Faxed/E-mailed |
| Aug 21, 2009 | Extension of Permit Request |
| Nov 17, 2009 | Enforcement Compliance Inspection Required |
| Nov 17, 2009 | Process Extension |
| Nov 17, 2009 | Extension Approved |
| Aug 10, 2012 | Extension Toll letter mailed |