| Action Date | Action Description |
|---|---|
| Dec 05, 2005 | Assent Application Received |
| Dec 06, 2005 | Administrative Review for Completeness |
| Dec 06, 2005 | Team Review for Completeness |
| Dec 06, 2005 | Application Accepted |
| Dec 06, 2005 | Category B assigned |
| Dec 19, 2005 | HPHC Historical Preservation No Effect |
| Dec 28, 2005 | 30 day Public Notice Issued |
| Jan 27, 2006 | Public Notice End Date |
| Mar 28, 2006 | Plans Received |
| Apr 28, 2006 | Biologist Report |
| Apr 28, 2006 | Engineering Report |
| May 03, 2006 | Supervisor Biologist SignOff |
| May 03, 2006 | Supervisor Engineer SignOff |
| May 04, 2006 | Executive Sign Off |
| May 11, 2006 | Ready to Schedule Semi-Monthly Meeting |
| May 11, 2006 | Mail Agenda Notice |
| May 23, 2006 | Semi-Monthly Meeting Held |
| May 23, 2006 | Council Approval Granted |
| May 23, 2006 | Semi-Monthly Meeting Date Scheduled |
| Jun 12, 2006 | Legal Response/Decision |
| Jun 20, 2006 | Typist for Processing |
| Jun 20, 2006 | Executive Sign Off |
| Jun 20, 2006 | Sent to Photo Copy |
| Jun 20, 2006 | Permit Approved |
| Jun 20, 2006 | Stipulation Package from Biologist |
| Jun 20, 2006 | Stipulation Package by Engineer |
| Jul 07, 2006 | US Army Corp of Engineers Permit Date |
| Jul 10, 2006 | US Army Corps of Engineers Approval Received |
| Jul 11, 2006 | Land Evidence Date |
| Jan 19, 2007 | Commencement of Work Notice received |