| Action Date | Action Description |
|---|---|
| Dec 27, 2005 | Assent Application Received |
| Dec 28, 2005 | Administrative Review for Completeness |
| Dec 29, 2005 | Team Review for Completeness |
| Dec 29, 2005 | Application Accepted |
| Jan 04, 2006 | Engineering Report |
| Jan 04, 2006 | Typist for Processing |
| Jan 04, 2006 | Executive Sign Off |
| Jan 04, 2006 | Sent to Photo Copy |
| Jan 04, 2006 | Permit Approved |
| Jan 10, 2006 | HPHC Historical Preservation No Effect |
| Apr 20, 2006 | Land Evidence Date |
| Oct 02, 2006 | Correspondence Received |
| Oct 02, 2006 | Correspondence Received |
| Oct 02, 2006 | Assent Correction Mailed |
| Oct 18, 2006 | Land Evidence Date |
| Oct 09, 2007 | Modification Request |
| Oct 10, 2007 | Administrative Review for Completeness |
| Jan 03, 2008 | Team Review for Completeness |
| Jan 30, 2008 | HPHC Historical Preservation No Effect |
| Feb 05, 2008 | Biologist Report |
| Feb 05, 2008 | Typist for Processing |
| Feb 05, 2008 | Executive Sign Off |
| Feb 05, 2008 | Sent to Photo Copy |
| Feb 05, 2008 | Modification Approved |
| Feb 20, 2008 | Land Evidence Date |
| Apr 14, 2008 | Modification Amended |
| Apr 14, 2008 | Modification Correction mailed |
| Apr 24, 2008 | Land Evidence Date |