| Action Date | Action Description |
|---|---|
| Dec 29, 2006 | Assent Application Received |
| Jan 02, 2007 | Administrative Review for Completeness |
| Jan 02, 2007 | Team Review for Completeness |
| Jan 02, 2007 | Application Accepted |
| Jan 22, 2007 | HPHC Historical Preservation No Effect |
| Feb 06, 2007 | Biologist Report |
| Feb 07, 2007 | Typist for Processing |
| Feb 07, 2007 | Permit Approved |
| Feb 08, 2007 | Executive Sign Off |
| Feb 08, 2007 | Sent to Photo Copy |
| Mar 01, 2007 | Land Evidence Date |
| Nov 08, 2007 | Commencement of Work Notice received |
| Feb 14, 2008 | Modification Request |
| Feb 18, 2008 | Administrative Review for Completeness |
| Feb 19, 2008 | Team Review for Completeness |
| Mar 11, 2008 | HPHC Historical Preservation No Effect |
| Apr 08, 2008 | Engineering Report |
| Apr 09, 2008 | Typist for Processing |
| Apr 09, 2008 | Executive Sign Off |
| Apr 09, 2008 | Sent to Photo Copy |
| Apr 09, 2008 | Modification Approved |
| May 07, 2008 | Land Evidence Date |