| Action Date | Action Description |
|---|---|
| Jan 30, 2008 | Assent Application Received |
| Jan 31, 2008 | Administrative Review for Completeness |
| Feb 01, 2008 | Team Review for Completeness |
| Feb 01, 2008 | Team Review for Completeness |
| Feb 04, 2008 | Deficient Application - Owner Notification Sent |
| Mar 14, 2008 | Correspondence Received |
| Mar 14, 2008 | Application Accepted |
| Mar 17, 2008 | Category A* (Docks) |
| Mar 21, 2008 | 30 day Public Notice Issued |
| Apr 09, 2008 | HPHC Historical Preservation No Effect |
| Apr 18, 2008 | Phone Call |
| Apr 18, 2008 | Objections/Comments Received |
| Apr 18, 2008 | Objections/Comments Received |
| Apr 21, 2008 | Public Notice End Date |
| Apr 30, 2008 | Objections/Comments Received |
| May 22, 2008 | US Army Corp of Engineers Permit Date |
| May 27, 2008 | US Army Corps of Engineers Approval Received |
| Jun 09, 2008 | Engineering Report |
| Jun 09, 2008 | Biologist Report |
| Jun 09, 2008 | Supervisor Engineer SignOff |
| Jun 11, 2008 | Supervisor Biologist SignOff |
| Jun 16, 2008 | Executive Signoff of Staff Reports |
| Jul 03, 2008 | Correspondence Received |
| Jul 09, 2008 | Ready to Schedule Semi-Monthly Meeting |
| Jul 09, 2008 | Mail Agenda Notice |
| Jul 22, 2008 | Semi-Monthly Meeting Held |
| Jul 22, 2008 | Council Approval Granted |
| Jul 22, 2008 | Semi-Monthly Meeting Date Scheduled |
| Aug 11, 2008 | Legal Response/Decision |
| Aug 26, 2008 | Additional Information Received |
| Aug 29, 2008 | Typist for Processing |
| Aug 29, 2008 | Executive Sign Off |
| Aug 29, 2008 | Sent to Photo Copy |
| Aug 29, 2008 | Permit Approved |
| Aug 29, 2008 | Stipulation Package from Biologist |
| Aug 29, 2008 | Stipulation Package by Engineer |
| Sep 08, 2008 | Land Evidence Date |
| Oct 31, 2008 | Commencement of Work Notice received |
| Jan 13, 2017 | Modification Request |
| Jan 13, 2017 | Administrative Review for Completeness |
| Jan 20, 2017 | Phone Call |
| Jan 26, 2017 | Team Review for Completeness |
| Jan 27, 2017 | Deficient Application - Owner Notification Sent |
| Feb 21, 2017 | Deficiency Response Received |
| Feb 22, 2017 | Team Review for Completeness |
| Feb 22, 2017 | Application Accepted |
| Mar 03, 2017 | HPHC Historical Preservation No Effect |
| Mar 20, 2017 | 30 day Public Notice Issued |
| Apr 20, 2017 | Public Notice End Date |
| Apr 27, 2017 | US Army Corps of Engineers Approval Received |
| May 19, 2017 | Plans Received |
| May 26, 2017 | Mail Agenda Notice |
| Jun 06, 2017 | Biologist Report |
| Jun 13, 2017 | Semi-Monthly Meeting Date Scheduled |
| Jun 13, 2017 | Council Approval Granted |
| Jun 14, 2017 | Stipulation Package from Biologist |
| Jun 14, 2017 | Typist for Processing |
| Jun 14, 2017 | Modification Approved |
| Jun 19, 2017 | Legal Response/Decision |
| Jul 13, 2017 | Land Evidence Date |