| Action Date | Action Description |
|---|---|
| Mar 13, 2008 | Preliminary Determination Request (Coastal) |
| Mar 13, 2008 | Administrative Review for Completeness |
| Mar 14, 2008 | Team Review for Completeness |
| Mar 14, 2008 | Team Review for Completeness |
| Mar 14, 2008 | Application Accepted |
| Mar 14, 2008 | Category A assigned |
| Apr 09, 2008 | HPHC Historical Preservation No Effect |
| Jun 26, 2008 | Additional Information Received |
| Jun 26, 2008 | Category B assigned |
| Jun 30, 2008 | 30 day Public Notice Issued |
| Jun 30, 2008 | HPHC Historical Preservation No Effect |
| Jul 21, 2008 | Correspondence Received |
| Jul 30, 2008 | Public Notice End Date |
| Aug 15, 2008 | Dock Meeting Scheduled (Admin) |
| Aug 26, 2008 | US Army Corp of Engineers Permit Date |
| Aug 27, 2008 | US Army Corps of Engineers Approval Received |
| Sep 04, 2008 | Additional Information Received |
| Sep 25, 2008 | Dock/1.1.6 Review approval |
| Sep 26, 2008 | Engineering Report |
| Sep 26, 2008 | Biologist Report |
| Oct 03, 2008 | Typist for Processing |
| Oct 03, 2008 | Executive Sign Off |
| Oct 03, 2008 | Sent to Photo Copy |
| Oct 03, 2008 | Permit Approved |
| Oct 08, 2008 | Land Evidence Date |
| Oct 14, 2008 | Water Quality Certification |