| Action Date | Action Description |
|---|---|
| Aug 08, 2008 | Correspondence Received |
| Aug 18, 2008 | Assent Application Received |
| Aug 19, 2008 | Administrative Review for Completeness |
| Aug 21, 2008 | Team Review for Completeness |
| Aug 28, 2008 | Team Review for Completeness |
| Aug 28, 2008 | Application Accepted |
| Aug 28, 2008 | Category A* (Docks) |
| Aug 29, 2008 | Additional Information Received |
| Sep 03, 2008 | Additional Information Received |
| Sep 04, 2008 | Additional Information Received |
| Sep 05, 2008 | 30 day Public Notice Issued |
| Sep 12, 2008 | HPHC Historical Preservation No Effect |
| Oct 05, 2008 | Public Notice End Date |
| Oct 06, 2008 | Objections/Comments Received |
| Oct 07, 2008 | Objections/Comments Received |
| Oct 27, 2008 | US Army Corp of Engineers Permit Date |
| Oct 29, 2008 | US Army Corps of Engineers Approval Received |
| Dec 01, 2008 | Biologist Report |
| Dec 01, 2008 | Engineering Report |
| Dec 02, 2008 | Plans Received |
| Dec 03, 2008 | Supervisor Biologist SignOff |
| Dec 11, 2008 | Supervisor Engineer SignOff |
| Dec 12, 2008 | Executive Signoff of Staff Reports |
| Dec 22, 2008 | Ready to Schedule Semi-Monthly Meeting |
| Dec 22, 2008 | Mail Agenda Notice |
| Dec 29, 2008 | Correspondence Received |
| Jan 13, 2009 | Council Approval Granted |
| Jan 13, 2009 | Semi-Monthly Meeting Held |
| Jan 13, 2009 | Semi-Monthly Meeting Date Scheduled |
| Jan 21, 2009 | Legal Response/Decision |
| Jan 29, 2009 | Plans Received |
| Jan 29, 2009 | Typist for Processing |
| Jan 29, 2009 | Executive Sign Off |
| Jan 29, 2009 | Sent to Photo Copy |
| Jan 29, 2009 | Permit Approved |
| Jan 29, 2009 | Stipulation Package from Biologist |
| Jan 29, 2009 | Stipulation Package by Engineer |
| Feb 10, 2009 | Land Evidence Date |