| Action Date | Action Description |
|---|---|
| Nov 06, 2008 | Assent Application Received |
| Nov 06, 2008 | Administrative Review for Completeness |
| Nov 26, 2008 | Team Review for Completeness |
| Nov 26, 2008 | Team Review for Completeness |
| Nov 26, 2008 | Deficient Application - Owner Notification Sent |
| Jan 15, 2009 | Deficiency Response Received |
| Jan 16, 2009 | Administrative Review for Completeness |
| Jan 16, 2009 | Team Review for Completeness |
| Jan 16, 2009 | Team Review for Completeness |
| Jan 16, 2009 | Application Accepted |
| Feb 06, 2009 | Engineering Report |
| Feb 09, 2009 | Typist for Processing |
| Feb 09, 2009 | Executive Sign Off |
| Feb 09, 2009 | Sent to Photo Copy |
| Feb 09, 2009 | Permit Approved |
| Feb 11, 2009 | Land Evidence Date |
| Jan 24, 2012 | Extension Toll letter mailed |
| Aug 29, 2012 | Commencement of Work Notice received |
| Aug 31, 2012 | Correspondence Received |