| Action Date | Action Description |
|---|---|
| Feb 03, 2009 | Assent Application Received |
| Feb 04, 2009 | Administrative Review for Completeness |
| Feb 05, 2009 | Team Review for Completeness |
| Feb 05, 2009 | Application Accepted |
| Feb 12, 2009 | HPHC Historical Preservation No Effect |
| Feb 18, 2009 | Typist for Processing |
| Feb 18, 2009 | Executive Sign Off |
| Feb 18, 2009 | Sent to Photo Copy |
| Feb 18, 2009 | Permit Approved |
| Feb 18, 2009 | Biologist Report |
| Mar 04, 2009 | Land Evidence Date |
| Nov 25, 2013 | Extension Toll letter mailed |
| Dec 06, 2013 | Modification Request |
| Dec 06, 2013 | Team Review for Completeness |
| Dec 10, 2013 | Administrative Review for Completeness |
| Dec 13, 2013 | Typist for Processing |
| Dec 13, 2013 | Modification Approved |
| Dec 18, 2013 | Biologist Report |
| Dec 19, 2013 | Executive Sign Off |
| Dec 19, 2013 | Sent to Photo Copy |
| Dec 30, 2013 | Land Evidence Date |