| Action Date | Action Description |
|---|---|
| Feb 13, 2009 | Assent Application Received |
| Feb 17, 2009 | Administrative Review for Completeness |
| Feb 17, 2009 | Additional Information Received |
| Feb 23, 2009 | Plans Received |
| Feb 25, 2009 | Application Accepted |
| Feb 25, 2009 | Team Review for Completeness |
| Feb 25, 2009 | Team Review for Completeness |
| Mar 31, 2009 | HPHC Historical Preservation No Effect |
| Sep 02, 2009 | Biologist Report |
| Sep 03, 2009 | Typist for Processing |
| Sep 03, 2009 | Permit Approved |
| Sep 04, 2009 | Executive Sign Off |
| Sep 04, 2009 | Sent to Photo Copy |
| Sep 04, 2009 | Correspondence Received |
| Sep 14, 2009 | Commencement of Work Notice received |
| Sep 15, 2009 | Land Evidence Date |