| Action Date | Action Description |
|---|---|
| Feb 19, 2009 | Maintenance Certification Request |
| Feb 19, 2009 | Administrative Review for Completeness |
| Feb 23, 2009 | Team Review for Completeness |
| Feb 23, 2009 | Team Review for Completeness |
| Feb 23, 2009 | Application Accepted |
| Mar 27, 2009 | Correspondence Mailed/Faxed/E-mailed |
| Mar 27, 2009 | Additional Information Requested from Applicant |
| Mar 31, 2009 | HPHC Historical Preservation No Effect |
| Apr 02, 2009 | Correspondence Mailed/Faxed/E-mailed |
| Apr 10, 2009 | Note to File |
| Jul 20, 2009 | Biologist Report |
| Jul 20, 2009 | Engineering Report |
| Jul 21, 2009 | Correspondence Received |
| Jul 22, 2009 | Typist for Processing |
| Jul 22, 2009 | Permit Approved |
| Jul 23, 2009 | Executive Sign Off |
| Aug 04, 2009 | Sent to Photo Copy |
| Aug 18, 2009 | Land Evidence Date |