| Action Date | Action Description |
|---|---|
| Jun 16, 2009 | Assent Application Received |
| Jun 18, 2009 | Administrative Review for Completeness |
| Jun 29, 2009 | Team Review for Completeness |
| Jun 29, 2009 | Team Review for Completeness |
| Jun 29, 2009 | Deficient Application - Owner Notification Sent |
| Jul 07, 2009 | Deficiency Response Received |
| Jul 08, 2009 | Team Review for Completeness |
| Jul 08, 2009 | Team Review for Completeness |
| Jul 08, 2009 | Application Accepted |
| Jul 20, 2009 | Engineering Report |
| Jul 22, 2009 | Biologist Report |
| Jul 23, 2009 | Typist for Processing |
| Jul 23, 2009 | Permit Approved |
| Jul 24, 2009 | Executive Sign Off |
| Jul 24, 2009 | Sent to Photo Copy |
| Aug 27, 2009 | HPHC Historical Preservation No Effect |
| Sep 18, 2009 | Duplicate Original Assent requested/mailed |
| Oct 02, 2009 | Land Evidence Date |