| Action Date | Action Description |
|---|---|
| Sep 21, 2009 | Assent Application Received |
| Sep 22, 2009 | Administrative Review for Completeness |
| Sep 22, 2009 | Team Review for Completeness |
| Sep 22, 2009 | Team Review for Completeness |
| Sep 22, 2009 | Application Accepted |
| Oct 20, 2009 | Additional Information Requested from Applicant |
| Oct 29, 2009 | Correspondence Received |
| Dec 18, 2009 | Plans Received |
| Dec 28, 2009 | Biologist Report |
| Dec 28, 2009 | Engineering Report |
| Dec 30, 2009 | Typist for Processing |
| Dec 30, 2009 | Permit Approved |
| Jan 27, 2010 | Land Evidence Date |
| Feb 25, 2010 | Modification Request |
| Mar 01, 2010 | Administrative Review for Completeness |
| Mar 01, 2010 | Team Review for Completeness |
| Mar 01, 2010 | Team Review for Completeness |
| Mar 11, 2010 | Engineering Report |
| Mar 11, 2010 | Biologist Report |
| Mar 15, 2010 | Modification Approved |
| Mar 26, 2010 | HPHC Historical Preservation No Effect |
| Jun 09, 2015 | Modification Request |
| Jun 10, 2015 | Administrative Review for Completeness |
| Jun 15, 2015 | Team Review for Completeness |
| Jun 15, 2015 | Biologist Report |
| Jun 15, 2015 | Typist for Processing |
| Jun 15, 2015 | Modification Approved |
| Jul 13, 2015 | Land Evidence Date |