| Action Date | Action Description |
|---|---|
| Mar 03, 2010 | Assent Application Received |
| Mar 03, 2010 | Category A* (Docks) |
| Mar 04, 2010 | Administrative Review for Completeness |
| Mar 08, 2010 | Team Review for Completeness |
| Mar 08, 2010 | Team Review for Completeness |
| Mar 09, 2010 | Application Accepted |
| Mar 16, 2010 | 30 day Public Notice Issued |
| Mar 25, 2010 | HPHC Historical Preservation No Effect |
| Apr 16, 2010 | Public Notice End Date |
| May 26, 2010 | US Army Corp of Engineers Permit Date |
| Jun 03, 2010 | US Army Corps of Engineers Approval Received |
| Jun 30, 2010 | Entry of Appearance Received |
| Jul 19, 2010 | Additional Information Received |
| Sep 28, 2010 | Engineering Report |
| Sep 29, 2010 | Biologist Report |
| Oct 04, 2010 | Supervisor Biologist SignOff |
| Oct 04, 2010 | Supervisor Engineer SignOff |
| Oct 06, 2010 | Executive Signoff of Staff Reports |
| Oct 15, 2010 | Ready to Schedule Semi-Monthly Meeting |
| Oct 15, 2010 | Mail Agenda Notice |
| Oct 19, 2010 | Continuance Requested |
| Oct 21, 2010 | Management Review |
| Oct 21, 2010 | Continuance request by applicant granted by Council |
| Oct 26, 2010 | Semi-Monthly Meeting Date Scheduled |
| Nov 03, 2010 | Ready to Schedule Semi-Monthly Meeting |
| Nov 03, 2010 | Mail Agenda Notice |
| Nov 16, 2010 | Semi-Monthly Meeting Held |
| Nov 16, 2010 | Council Approval Granted |
| Nov 16, 2010 | Semi-Monthly Meeting Date Scheduled |
| Dec 13, 2010 | Legal Response/Decision |
| Dec 14, 2010 | Additional Information Received |
| Dec 14, 2010 | Stipulation Package from Biologist |
| Dec 14, 2010 | Stipulation Package by Engineer |
| Dec 16, 2010 | Typist for Processing |
| Dec 17, 2010 | Permit Approved |
| Dec 20, 2010 | Executive Sign Off |
| Dec 20, 2010 | Sent to Photo Copy |
| Jan 03, 2011 | Land Evidence Date |