| Action Date | Action Description |
|---|---|
| Aug 31, 2010 | Assent Application Received |
| Sep 02, 2010 | Administrative Review for Completeness |
| Sep 03, 2010 | Additional Information Received |
| Sep 14, 2010 | Application Accepted |
| Sep 14, 2010 | Team Review for Completeness |
| Sep 14, 2010 | Team Review for Completeness |
| Sep 27, 2010 | Typist for Processing |
| Sep 28, 2010 | Engineering Report |
| Sep 28, 2010 | Permit Approved |
| Sep 29, 2010 | Executive Sign Off |
| Sep 30, 2010 | Sent to Photo Copy |
| Jun 04, 2012 | US Army Corps of Engineers Approval Received |