| Action Date | Action Description |
|---|---|
| Mar 07, 2011 | Assent Application Received |
| Mar 08, 2011 | Administrative Review for Completeness |
| Mar 08, 2011 | Team Review for Completeness |
| Mar 08, 2011 | Application Accepted |
| Mar 10, 2011 | 30 day Public Notice Issued |
| Mar 17, 2011 | HPHC Historical Preservation No Effect |
| Mar 28, 2011 | Public Notice End Date Extension Granted |
| Apr 11, 2011 | Public Notice End Date |
| Apr 11, 2011 | Objections/Comments Received |
| Apr 11, 2011 | Objections/Comments Received |
| May 02, 2011 | US Army Corps of Engineers Approval Received |
| May 02, 2011 | Public Notice End Date Extension Granted |
| May 04, 2011 | Objections/Comments Received |
| May 23, 2011 | Engineering Report |
| May 24, 2011 | Objections/Comments Received |
| Jun 03, 2011 | Executive Signoff of Staff Reports |
| Jun 08, 2011 | Ready to Schedule Semi-Monthly Meeting |
| Jun 14, 2011 | Mail Agenda Notice |
| Jun 28, 2011 | Council Approval Granted |
| Jun 28, 2011 | Semi-Monthly Meeting Date Scheduled |
| Jun 28, 2011 | Semi-Monthly Meeting Held |
| Jul 12, 2011 | Legal Response/Decision |
| Aug 17, 2011 | Under Review/Decision |
| Aug 17, 2011 | Stipulation Package from Biologist |
| Aug 17, 2011 | Stipulation Package by Engineer |
| Sep 09, 2011 | Category B assigned |
| Sep 09, 2011 | Typist for Processing |
| Sep 09, 2011 | Permit Approved |
| Sep 12, 2011 | Executive Sign Off |
| Sep 12, 2011 | Sent to Photo Copy |
| Sep 30, 2011 | Land Evidence Date |
| Sep 30, 2011 | Commencement of Work Notice received |