| Action Date | Action Description |
|---|---|
| Apr 13, 2011 | Assent Application Received |
| Apr 13, 2011 | Administrative Review for Completeness |
| May 19, 2011 | Team Review for Completeness |
| May 19, 2011 | Team Review for Completeness |
| May 19, 2011 | Category B assigned |
| May 19, 2011 | Application Accepted |
| Jun 03, 2011 | 30 day Public Notice Issued |
| Jun 13, 2011 | HPHC Historical Preservation No Effect |
| Jul 03, 2011 | Public Notice End Date |
| Jul 22, 2011 | Engineering Report |
| Jul 26, 2011 | Biologist Report |
| Jul 29, 2011 | Executive Signoff of Staff Reports |
| Aug 02, 2011 | Ready to Schedule Semi-Monthly Meeting |
| Aug 02, 2011 | Public Hearing Notices Mailed |
| Aug 23, 2011 | Council Approval Granted |
| Aug 23, 2011 | Semi-Monthly Meeting Date Scheduled |
| Aug 23, 2011 | Semi-Monthly Meeting Held |
| Sep 20, 2011 | 30 Day Appeal Notification to Owner |
| Sep 20, 2011 | Stipulation Package from Biologist |
| Sep 20, 2011 | Stipulation Package by Engineer |
| Sep 20, 2011 | Legal Response/Decision |
| Sep 21, 2011 | Typist for Processing |
| Sep 21, 2011 | Executive Sign Off |
| Sep 21, 2011 | Sent to Photo Copy |
| Sep 21, 2011 | Permit Approved |
| Sep 26, 2011 | Land Evidence Date |
| Nov 26, 2013 | HPHC Historical Preservation No Effect |