| Action Date | Action Description |
|---|---|
| Sep 10, 2012 | Assent Application Received |
| Sep 11, 2012 | Administrative Review for Completeness |
| Sep 17, 2012 | Team Review for Completeness |
| Sep 17, 2012 | Team Review for Completeness |
| Sep 17, 2012 | Deficient Application - Owner Notification Sent |
| Sep 20, 2012 | Deficient Application Picked Up |
| Oct 15, 2012 | Deficiency Response Received |
| Oct 18, 2012 | Team Review for Completeness |
| Oct 18, 2012 | Team Review for Completeness |
| Oct 18, 2012 | Application Accepted |
| Nov 01, 2012 | HPHC Historical Preservation No Effect |
| Jan 28, 2013 | Additional Information Received |
| Mar 04, 2013 | Additional Information Received |
| Mar 11, 2013 | Engineering Report |
| Mar 12, 2013 | Biologist Report |
| Mar 13, 2013 | Typist for Processing |
| Mar 14, 2013 | Executive Sign Off |
| Mar 14, 2013 | Sent to Photo Copy |
| Mar 14, 2013 | Permit Approved |
| Mar 18, 2013 | Land Evidence Date |
| Aug 09, 2016 | Expiration of Assent/End of Tolling Legislation |
| Jun 12, 2018 | Expiration of Assent/End of Tolling Legislation |
| Apr 10, 2019 | Extension of Permit Request |
| May 24, 2019 | Enforcement Compliance Inspection Required |
| May 28, 2019 | Process Extension |
| May 28, 2019 | Extension Approved |
| Aug 05, 2021 | Phone Call |