| Action Date | Action Description |
|---|---|
| Oct 11, 2012 | Assent Application Received |
| Oct 12, 2012 | Administrative Review for Completeness |
| Oct 12, 2012 | Team Review for Completeness |
| Oct 12, 2012 | Team Review for Completeness |
| Oct 12, 2012 | Application Accepted |
| Oct 15, 2012 | 30 day Public Notice Issued |
| Nov 01, 2012 | HPHC Historical Preservation No Effect |
| Nov 15, 2012 | Public Notice End Date |
| Dec 03, 2012 | Typist for Processing |
| Dec 03, 2012 | Executive Sign Off |
| Dec 03, 2012 | Sent to Photo Copy |
| Dec 03, 2012 | Permit Approved |
| Dec 03, 2012 | Biologist Report |
| Dec 03, 2012 | Engineering Report |
| Dec 18, 2012 | Land Evidence Date |