| Action Date | Action Description |
|---|---|
| Oct 12, 2012 | Dredge Application |
| Oct 15, 2012 | Administrative Review for Completeness |
| Oct 15, 2012 | Team Review for Completeness |
| Oct 15, 2012 | Application Accepted |
| Oct 24, 2012 | Joint Public Notice |
| Oct 25, 2012 | HPHC Historical Preservation No Effect |
| Nov 20, 2012 | Dredge Report |
| Nov 20, 2012 | DEM Dredge Permit |
| Nov 26, 2012 | Typist for Processing |
| Nov 26, 2012 | Site Inspection |
| Nov 26, 2012 | Permit Approved |
| Nov 27, 2012 | Executive Sign Off |
| Nov 27, 2012 | Sent to Photo Copy |
| Nov 30, 2012 | US Army Corps of Engineers Approval Received |
| Jan 28, 2013 | Site Inspection |
| Jan 28, 2013 | Site Inspection |
| Feb 22, 2013 | Correspondence Mailed/Faxed/E-mailed |
| Apr 24, 2013 | CAD Cell Fee Due-Final |