| Action Date | Action Description |
|---|---|
| Oct 12, 2012 | Assent Application Received |
| Oct 15, 2012 | Administrative Review for Completeness |
| Dec 26, 2012 | Additional Information Received |
| Jan 31, 2013 | Additional Information Received |
| Apr 02, 2013 | 30 day Public Notice Issued |
| Apr 02, 2013 | Application Accepted |
| May 02, 2013 | Public Notice End Date |
| May 09, 2013 | Biologist Report |
| May 09, 2013 | Engineering Report |
| May 17, 2013 | Typist for Processing |
| May 17, 2013 | Permit Approved |
| May 20, 2013 | Executive Sign Off |
| May 20, 2013 | Sent to Photo Copy |
| May 22, 2013 | Land Evidence Date |
| Jun 03, 2013 | US Army Corps of Engineers Approval Received |