| Action Date | Action Description |
|---|---|
| Dec 06, 2012 | Assent Application Received |
| Dec 07, 2012 | Administrative Review for Completeness |
| Dec 07, 2012 | Team Review for Completeness |
| Dec 07, 2012 | Team Review for Completeness |
| Dec 07, 2012 | Application Accepted |
| Dec 14, 2012 | Engineering Report |
| Dec 14, 2012 | Biologist Report |
| Dec 17, 2012 | Typist for Processing |
| Dec 17, 2012 | Permit Approved |
| Dec 18, 2012 | Executive Sign Off |
| Dec 18, 2012 | Sent to Photo Copy |
| Dec 19, 2012 | HPHC Historical Preservation No Effect |
| Mar 27, 2013 | Land Evidence Date |