| Action Date | Action Description |
|---|---|
| Feb 26, 2013 | Assent Application Received |
| Feb 26, 2013 | Administrative Review for Completeness |
| Feb 27, 2013 | Team Review for Completeness |
| Feb 27, 2013 | Application Accepted |
| Mar 15, 2013 | 30 day Public Notice Issued |
| Mar 19, 2013 | HPHC Historical Preservation No Effect |
| Apr 08, 2013 | Public Notice End Date Extension Granted |
| Apr 15, 2013 | Public Notice End Date |
| May 06, 2013 | Biologist Report |
| May 06, 2013 | Engineering Report |
| May 08, 2013 | Typist for Processing |
| May 08, 2013 | Permit Approved |
| May 08, 2013 | Category A* (Docks) |
| May 09, 2013 | US Army Corps of Engineers Approval Received |
| May 09, 2013 | Executive Sign Off |
| May 09, 2013 | Sent to Photo Copy |
| Jun 12, 2013 | Land Evidence Date |