| Jun 26, 2013 | Maintenance Certification Request |
| Jun 26, 2013 | Administrative Review for Completeness |
| Jul 01, 2013 | Team Review for Completeness |
| Jul 01, 2013 | Team Review for Completeness |
| Jul 01, 2013 | Application Accepted |
| Jul 01, 2013 | Correspondence Received |
| Jul 01, 2013 | Mail Agenda Notice |
| Jul 09, 2013 | Engineering Report |
| Jul 11, 2013 | Stipulation Package by Engineer |
| Jul 17, 2013 | Council Approval Granted |
| Jul 17, 2013 | Semi-Monthly Meeting Date Scheduled |
| Jul 18, 2013 | Typist for Processing |
| Jul 18, 2013 | Executive Sign Off |
| Jul 18, 2013 | Sent to Photo Copy |
| Jul 18, 2013 | Permit Approved |
| Jul 18, 2013 | Pre-construction requirement by CRMC staff |
| Jul 23, 2013 | Water Quality Certification |
| Jul 24, 2013 | HPHC Historical Preservation No Effect |
| Jul 31, 2013 | Legal Response/Decision |
| Aug 13, 2013 | 30 Day Appeal Notification to Owner |
| Oct 07, 2013 | Objections/Comments Received |
| Nov 13, 2013 | Modification Request |
| Nov 13, 2013 | Administrative Review for Completeness |
| Nov 14, 2013 | Team Review for Completeness |
| Nov 14, 2013 | Biologist Report |
| Nov 14, 2013 | Letter of Authorization |
| Dec 18, 2013 | Modification Request |
| Dec 24, 2013 | Administrative Review for Completeness |
| Dec 24, 2013 | Team Review for Completeness |
| Dec 24, 2013 | Biologist Report |
| Dec 24, 2013 | Typist for Processing |
| Dec 24, 2013 | Letter of Authorization |
| Dec 26, 2013 | Executive Sign Off |
| Dec 26, 2013 | Sent to Photo Copy |
| Jul 25, 2014 | Objections/Comments Received |