| Action Date | Action Description |
|---|---|
| Jan 14, 2014 | Assent Application Received |
| Jan 15, 2014 | Administrative Review for Completeness |
| Feb 10, 2014 | Team Review for Completeness |
| Feb 10, 2014 | Application Accepted |
| Feb 10, 2014 | Category A* (Docks) |
| Feb 20, 2014 | HPHC Historical Preservation No Effect |
| May 08, 2014 | 30 day Public Notice Issued |
| Jun 08, 2014 | Public Notice End Date |
| Jun 09, 2014 | Objections/Comments Received |
| Jun 09, 2014 | Plans Received |
| Jun 17, 2014 | Biologist Report |
| Jun 17, 2014 | Engineering Report |
| Jun 26, 2014 | Typist for Processing |
| Jun 26, 2014 | Sent to Photo Copy |
| Jun 26, 2014 | Permit Approved |
| Jun 27, 2014 | Executive Sign Off |
| Jul 03, 2014 | Land Evidence Date |
| Jul 07, 2014 | US Army Corps of Engineers Approval Received |