| Action Date | Action Description |
|---|---|
| Jan 21, 2015 | Assent Application Received |
| Jan 21, 2015 | Administrative Review for Completeness |
| Jan 30, 2015 | Team Review for Completeness |
| Jan 30, 2015 | Application Accepted |
| Feb 03, 2015 | Engineering Report |
| Feb 19, 2015 | HPHC Historical Preservation No Effect |
| Feb 20, 2015 | 30 day Public Notice Issued |
| Mar 20, 2015 | Public Notice End Date |
| Apr 06, 2015 | Biologist Report |
| May 04, 2015 | US Army Corps of Engineers Approval Received |
| Jun 16, 2015 | Plans Received |
| Jun 18, 2015 | Typist for Processing |
| Jun 19, 2015 | Executive Sign Off |
| Jun 19, 2015 | Sent to Photo Copy |
| Jun 19, 2015 | Permit Approved |
| Dec 03, 2015 | Land Evidence Date |
| Dec 30, 2015 | Category A* (Docks) |