| Action Date | Action Description |
|---|---|
| Oct 20, 2015 | Administrative Review for Completeness |
| Oct 22, 2015 | Team Review for Completeness |
| Oct 22, 2015 | Team Review for Completeness |
| Oct 22, 2015 | Additional Information Received |
| Oct 22, 2015 | Application Accepted |
| Oct 22, 2015 | Category B assigned |
| Nov 30, 2015 | Additional Information Requested from Applicant |
| Nov 30, 2015 | HPHC Historical Preservation No Effect |
| Mar 11, 2016 | Plans Received |
| Jun 09, 2016 | Plans Received |
| Jul 07, 2016 | 30 day Public Notice Issued |
| Aug 07, 2016 | Public Notice End Date |
| Sep 07, 2016 | Plans Received |
| Oct 07, 2016 | Water Quality Certification |
| Dec 19, 2016 | Dock/1.1.6 Review approval |
| Feb 21, 2017 | Biologist Report |
| Feb 24, 2017 | Engineering Report |
| Feb 24, 2017 | Typist for Processing |
| Feb 24, 2017 | Executive Sign Off |
| Feb 24, 2017 | Sent to Photo Copy |
| Feb 24, 2017 | Permit Approved |
| Mar 27, 2017 | Land Evidence Date |
| May 01, 2017 | Correspondence Received |
| May 19, 2017 | Additional Information Received |
| May 22, 2017 | Additional Information Received |
| May 27, 2017 | Land Evidence Date |