| Action Date | Action Description |
|---|---|
| Enforcement Compliance Inspection Required | |
| Feb 09, 2016 | Assent Application Received |
| Feb 09, 2016 | Administrative Review for Completeness |
| Feb 10, 2016 | Team Review for Completeness |
| Feb 10, 2016 | Team Review for Completeness |
| Feb 10, 2016 | Application Accepted |
| Mar 01, 2016 | Additional Information Requested from Applicant |
| Mar 08, 2016 | HPHC Historical Preservation No Effect |
| Mar 11, 2016 | Additional Information Received |
| Mar 21, 2016 | 30 day Public Notice Issued |
| Apr 13, 2016 | Objections/Comments Received |
| Apr 20, 2016 | Objections/Comments Received |
| Apr 21, 2016 | Public Notice End Date |
| Oct 26, 2016 | Additional Information Requested from Applicant |
| Dec 05, 2016 | 30-Day Notification of Cancellation letter |
| Dec 21, 2016 | Plans Received |
| Apr 13, 2017 | Mail Agenda Notice |
| Apr 13, 2017 | Entry of Appearance Received |
| Apr 24, 2017 | Letter of Support for Project |
| Apr 28, 2017 | Biologist Report |
| Apr 28, 2017 | Engineering Report |
| May 02, 2017 | Correspondence Received |
| May 09, 2017 | Council Approval Granted |
| May 09, 2017 | Semi-Monthly Meeting Date Scheduled |
| Oct 18, 2017 | Legal Response/Decision |
| Oct 18, 2017 | 30 Day Appeal Notification to Owner |
| Jul 25, 2018 | Stipulation Package from Biologist |
| Jul 26, 2018 | Stipulation Package by Engineer |
| Jul 26, 2018 | Typist for Processing |
| Jul 26, 2018 | Executive Sign Off |
| Jul 26, 2018 | Sent to Photo Copy |
| Jul 26, 2018 | Permit Approved |
| Aug 14, 2018 | Land Evidence Date |
| Apr 19, 2021 | Extension of Permit Request |
| Apr 29, 2021 | Enforcement Compliance Inspection Required |
| May 13, 2021 | Process Extension |
| May 13, 2021 | Extension Approved |
| Jul 21, 2021 | Commencement of Work Notice received |
| Mar 22, 2022 | Modification Request |
| Apr 15, 2022 | Administrative Review for Completeness |
| Apr 21, 2022 | Bio Team Review for Completeness |
| Apr 22, 2022 | Project Manager |
| Apr 25, 2022 | Extension of Permit Request |
| May 10, 2022 | Additional Information Requested from Applicant |
| May 11, 2022 | HPHC Historical Preservation No Effect |
| May 11, 2022 | HPHC Review Pending |
| May 23, 2022 | Biologist Report |
| May 24, 2022 | Modification Approved |
| Jun 01, 2022 | Land Evidence Date |
| Nov 25, 2022 | Enforcement Compliance Inspection Required |
| Nov 29, 2022 | Process Extension |
| Nov 30, 2022 | Extension Approved |
| Feb 27, 2023 | Extension of Permit Request |
| May 22, 2023 | Enforcement Compliance Inspection Required |
| Jul 07, 2023 | Process Extension |
| Jul 07, 2023 | Extension Approved |
| May 23, 2024 | Extension of Permit Request |