| Action Date | Action Description |
|---|---|
| Feb 20, 2017 | Assent Application Received |
| Feb 22, 2017 | Administrative Review for Completeness |
| Feb 23, 2017 | Team Review for Completeness |
| Feb 23, 2017 | Team Review for Completeness |
| Feb 23, 2017 | Application Accepted |
| Apr 05, 2017 | HPHC Historical Preservation No Effect |
| Aug 11, 2017 | Additional Information Received |
| Sep 08, 2017 | Engineering Report |
| Sep 11, 2017 | Typist for Processing |
| Sep 11, 2017 | Executive Sign Off |
| Sep 11, 2017 | Sent to Photo Copy |
| Sep 11, 2017 | Permit Approved |
| Nov 13, 2017 | Land Evidence Date |
| Sep 26, 2018 | Modification Request |
| Sep 26, 2018 | Administrative Review for Completeness |
| Oct 05, 2018 | Team Review for Completeness |
| Oct 05, 2018 | Application Accepted |
| Oct 19, 2018 | Engineering Report |
| Oct 19, 2018 | Modification Approved |
| Oct 19, 2018 | HPHC Historical Preservation No Effect |
| Nov 02, 2018 | Land Evidence Date |