| Action Date | Action Description |
|---|---|
| Dock Post-Construction Certification by Engineer received. | |
| Aug 08, 2017 | Category A* (Docks) |
| Aug 08, 2017 | Assent Application Received |
| Aug 08, 2017 | Administrative Review for Completeness |
| Aug 08, 2017 | Team Review for Completeness |
| Aug 08, 2017 | Application Accepted |
| Aug 23, 2017 | HPHC Historical Preservation No Effect |
| Aug 24, 2017 | 30 day Public Notice Issued |
| Sep 25, 2017 | Public Notice End Date |
| Sep 25, 2017 | Dock Meeting -- Approval |
| Oct 11, 2017 | Plans Received |
| Oct 17, 2017 | Biologist Report |
| Oct 19, 2017 | Typist for Processing |
| Oct 19, 2017 | Executive Sign Off |
| Oct 19, 2017 | Sent to Photo Copy |
| Oct 19, 2017 | Permit Approved |
| Feb 19, 2018 | Land Evidence Date |