| Action Date | Action Description |
|---|---|
| Dec 13, 2017 | Assent Application Received |
| Dec 13, 2017 | Administrative Review for Completeness |
| Dec 14, 2017 | Category A* (Docks) |
| Dec 14, 2017 | Team Review for Completeness |
| Dec 14, 2017 | Application Accepted |
| Jan 08, 2018 | HPHC Historical Preservation No Effect |
| Jan 09, 2018 | 30 day Public Notice Issued |
| Jan 31, 2018 | Objections/Comments Received |
| Feb 05, 2018 | Objections/Comments Received |
| Feb 10, 2018 | Public Notice End Date |
| Mar 22, 2018 | Correspondence Mailed/Faxed/E-mailed |
| May 17, 2018 | 30-Day Notification of Cancellation letter |
| Jun 15, 2018 | Correspondence Received |
| Jun 28, 2018 | Additional Information Requested from Applicant |
| Aug 27, 2018 | Plans Received |
| Oct 24, 2018 | Entry of Appearance Received |
| Dec 06, 2018 | Correspondence Received |
| Jan 24, 2019 | Comments Received |
| Jan 25, 2019 | Comments Received |
| Feb 06, 2019 | Additional Information Received |
| Feb 13, 2019 | Objections/Comments Received |
| May 07, 2019 | Additional Information Received |
| May 30, 2019 | Additional Information Requested from Applicant |
| Jul 24, 2019 | Additional Information Requested from Applicant |
| Oct 15, 2019 | Correspondence Mailed/Faxed/E-mailed |
| Sep 17, 2020 | Additional Information Received |
| Sep 22, 2020 | Additional Information Received |
| Oct 01, 2020 | Plans Received |
| Jan 21, 2021 | Additional Information Requested from Applicant |
| Mar 01, 2021 | Plans Received |
| Mar 30, 2021 | Correspondence Received |
| Mar 30, 2021 | Correspondence Mailed/Faxed/E-mailed |
| Apr 29, 2021 | Correspondence Mailed/Faxed/E-mailed |
| May 06, 2021 | Biologist Report |
| May 10, 2022 | Semi-Monthly Meeting Date Scheduled |
| May 24, 2022 | Semi-Monthly Meeting Date Scheduled |
| Jun 08, 2022 | Mail Agenda Notice |
| Jun 30, 2022 | Council Approval Granted |
| Jun 30, 2022 | Semi-Monthly Meeting Date Scheduled |
| Jul 06, 2022 | Stipulation Package from Biologist |
| Sep 06, 2022 | Additional Information Received |
| Sep 13, 2022 | Legal Response/Decision |
| Sep 20, 2022 | Permit Mailed |
| Sep 20, 2022 | Typist for Processing |
| Sep 20, 2022 | Executive Sign Off |
| Sep 20, 2022 | Sent to Photo Copy |
| Sep 20, 2022 | Permit Mailed |
| Sep 20, 2022 | Permit Approved |
| Sep 28, 2022 | Land Evidence Date |
| Feb 21, 2023 | Dock Post-Construction Certification by Engineer received. |