| Action Date | Action Description |
|---|---|
| Dec 18, 2017 | Assent Application Received |
| Dec 18, 2017 | Administrative Review for Completeness |
| Dec 19, 2017 | Team Review for Completeness |
| Dec 19, 2017 | Application Accepted |
| Dec 27, 2017 | Additional Information Requested from Applicant |
| Jan 12, 2018 | Plans Received |
| Jan 26, 2018 | HPHC Historical Preservation No Effect |
| Jan 29, 2018 | Biologist Report |
| Jan 29, 2018 | Typist for Processing |
| Jan 29, 2018 | Executive Sign Off |
| Jan 29, 2018 | Sent to Photo Copy |
| Jan 29, 2018 | Permit Approved |
| Feb 21, 2018 | Land Evidence Date |