| Action Date | Action Description |
|---|---|
| Assent Requirement | |
| Legal Response/Decision | |
| Jul 17, 2018 | Assent Application Received |
| Jul 17, 2018 | Administrative Review for Completeness |
| Jul 27, 2018 | Plans Received |
| Sep 10, 2018 | Application Accepted |
| Sep 10, 2018 | Team Review for Completeness |
| Sep 10, 2018 | Category B assigned |
| Oct 03, 2018 | 30 day Public Notice Issued |
| Oct 30, 2018 | Objections/Comments Received |
| Nov 02, 2018 | Public Notice End Date |
| Mar 06, 2019 | Plans Received |
| Mar 07, 2019 | Supervisor Engineer SignOff |
| Mar 07, 2019 | Supervisor Biologist SignOff |
| Mar 07, 2019 | Engineering Report |
| Mar 12, 2019 | Executive Signoff of Staff Reports |
| Mar 15, 2019 | Ready to Schedule Semi-Monthly Meeting |
| Mar 15, 2019 | Mail Agenda Notice |
| Mar 22, 2019 | Continuance Requested |
| Mar 25, 2019 | Management Review |
| Mar 25, 2019 | Continuance request by applicant granted by Director |
| Mar 26, 2019 | Semi-Monthly Meeting Date Scheduled |
| Mar 29, 2019 | Ready to Schedule Semi-Monthly Meeting |
| Mar 29, 2019 | Mail Agenda Notice |
| Apr 09, 2019 | Semi-Monthly Meeting Date Scheduled |
| Apr 23, 2019 | Council Approval Granted |
| May 08, 2019 | Typist for Processing |
| May 08, 2019 | Executive Sign Off |
| May 08, 2019 | Sent to Photo Copy |
| May 08, 2019 | Permit Approved |
| May 20, 2019 | Land Evidence Date |