| Action Date | Action Description |
|---|---|
| Feb 12, 2020 | Freshwater Wetland - Preliminary Determination |
| Feb 13, 2020 | Administrative Review for Completeness |
| Feb 14, 2020 | Eng Team Review for Completeness |
| Feb 14, 2020 | Application Accepted |
| Mar 06, 2020 | Project Manager |
| Mar 11, 2020 | HPHC Historical Preservation No Effect |
| Mar 11, 2020 | HPHC Review Pending |
| Jun 17, 2020 | Biologist Report |
| Jun 17, 2020 | Typist for Processing |
| Jun 17, 2020 | Executive Sign Off |
| Jun 17, 2020 | Sent to Photo Copy |
| Jun 17, 2020 | Permit Approved |
| Nov 17, 2022 | Extension of Permit Request |
| Dec 28, 2022 | Extension Approved |