| Action Date | Action Description |
|---|---|
| Feb 24, 2020 | Assent Application Received |
| Feb 25, 2020 | Administrative Review for Completeness |
| Mar 05, 2020 | Bio Team Review for Completeness |
| Mar 06, 2020 | Deficient Application - Owner Notification Sent |
| Mar 10, 2020 | Deficient Application Picked Up |
| Apr 22, 2020 | Deficiency Response Received |
| Apr 23, 2020 | Bio Team Review for Completeness |
| Apr 23, 2020 | Application Accepted |
| Apr 23, 2020 | Project Manager |
| Apr 27, 2020 | HPHC Historical Preservation No Effect |
| Apr 28, 2020 | Additional Information Requested from Applicant |
| May 18, 2020 | Plans Received |
| Jun 04, 2020 | Typist for Processing |
| Jun 04, 2020 | Permit Approved |
| Jun 04, 2020 | Executive Sign Off |
| Jun 04, 2020 | Sent to Photo Copy |
| Jun 04, 2020 | Biologist Report |
| Aug 12, 2020 | Land Evidence Date |