| Action Date | Action Description |
|---|---|
| Feb 27, 2020 | Assent Application Received |
| Feb 28, 2020 | Administrative Review for Completeness |
| Mar 03, 2020 | Eng Team Review for Completeness |
| Mar 03, 2020 | Bio Team Review for Completeness |
| Mar 03, 2020 | Application Accepted |
| Apr 01, 2020 | Project Manager |
| Apr 08, 2020 | Additional Information Requested from Applicant |
| Apr 15, 2020 | Additional Information Received |
| Apr 16, 2020 | HPHC Historical Preservation No Effect |
| Apr 16, 2020 | HPHC Review Pending |
| Apr 24, 2020 | Additional Information Received |
| Apr 27, 2020 | 30 day Public Notice Issued |
| May 27, 2020 | Public Notice End Date |
| Jul 09, 2020 | Additional Information Received |
| Aug 04, 2020 | Additional Information Received |
| Aug 05, 2020 | Engineering Report |
| Aug 05, 2020 | Biologist Report |
| Aug 06, 2020 | Dock/1.1.6 Review approval |
| Aug 06, 2020 | Typist for Processing |
| Aug 06, 2020 | Executive Sign Off |
| Aug 06, 2020 | Sent to Photo Copy |
| Aug 06, 2020 | Permit Approved |
| Nov 30, 2020 | Commencement of Work Notice received |
| Feb 10, 2021 | Modification Request |
| Feb 12, 2021 | Administrative Review for Completeness |
| Feb 17, 2021 | Bio Team Review for Completeness |
| Feb 17, 2021 | Project Manager |
| Feb 17, 2021 | Biologist Report |
| Feb 17, 2021 | Typist for Processing |
| Feb 17, 2021 | Executive Sign Off |
| Feb 17, 2021 | Sent to Photo Copy |
| Feb 17, 2021 | Modification Approved |
| Sep 07, 2022 | Modification Request |
| Sep 09, 2022 | Administrative Review for Completeness |
| Sep 12, 2022 | Eng Team Review for Completeness |
| Sep 13, 2022 | Project Manager |
| Sep 15, 2022 | Engineering Report |
| Sep 16, 2022 | Typist for Processing |
| Sep 16, 2022 | Executive Sign Off |
| Sep 16, 2022 | Sent to Photo Copy |
| Sep 16, 2022 | Modification Approved |
| Sep 30, 2022 | HPHC Historical Preservation No Effect |
| Jul 13, 2023 | Extension of Permit Request |
| Aug 02, 2023 | Extension Approved |
| Jun 25, 2024 | Extension of Permit Request |
| Jun 25, 2024 | Extension Approved |